A geotechnical report can look like a stack of tables. But a few pages tell you whether your plot is straightforward or difficult, and what the foundation will cost. This guide explains the key parts so you can ask better questions of your engineer.
Parts of a typical report
- Site and project description.
- Field investigation method.
- Borehole logs with layers and N-values.
- Laboratory test summary.
- Analysis: bearing capacity, settlement, pile capacity.
- Recommendations and limitations.
Understanding the borehole log
Each line shows depth, soil description (clay, silt, sand), SPT blow counts and sample type. Low N-values in clay indicate soft soil, and loose sand with low N below the water table can raise liquefaction concern in earthquakes. Look for sudden changes with depth, since they influence pile length.
SPT N-value in plain words
The N-value is the number of hammer blows needed to drive the sampler 300 mm. Higher values generally mean stronger or denser soil. Engineers apply corrections and interpret the values with soil type; they are not used blindly.
Bearing capacity and settlement
Allowable bearing capacity is the pressure the soil can safely support without failure and with acceptable settlement. For clay, settlement over time (consolidation) can govern the design even when strength looks adequate.
Groundwater
Shallow groundwater influences excavation, basement design, uplift and construction cost. Make sure the report states the level measured and the season.
Questions to ask your engineer
- Which layer will carry the foundation?
- What settlement is expected?
- Is liquefaction considered?
- Do we need piles, and how long?
- What dewatering or shoring is needed?
Need help? Our geotechnical team can review a report and explain the implications. See also soil investigation: the first step to a safe building.
Talk to a specialist engineer
Share your plot and building details and our engineers will reply with a clear, scoped proposal.
Frequently asked questions
What does an SPT value of 10 mean?
It indicates medium-stiff clay or medium-dense sand depending on soil type. Interpretation requires the soil description and corrections.
Why does groundwater matter?
It affects soil strength, excavation safety, uplift on basements and construction methods.
Can I get a second opinion on my soil report?
Yes. A geotechnical engineer can review the report and recommend additional tests if needed.
How long is a soil report valid?
It remains valid for the investigated site if conditions have not changed, but design changes or site works may require updates.
Related reading
Planning a project in Bangladesh?
Our specialist engineers apply exactly what this article covers to real projects — from structural & foundation design to 3D visualisation. See our completed projects.
Prof. Dr. Ahasanul Kabir
Former Professor of Civil Engineering Department, BUET
This article was reviewed for technical accuracy by Prof. Dr. Ahasanul Kabir, ensuring it reflects sound engineering practice and Bangladesh National Building Code (BNBC) standards.